Insulated Storage Tank Fabrication & Erection

Fabrication, insulation and craned erection of a large vertical storage tank, executed as a night lift to work around the site's daytime operations.

Crane lifting a large insulated and clad cylindrical storage tank at night while the site team observes

Scope#

Complete fabrication of a large vertical storage tank, insulated and clad before erection, then lifted and set as a single assembly.

Insulating and cladding at ground level rather than at height is the decision that shapes this kind of job. It removes most of the working-at-height exposure from the insulation scope, gives the crew proper access to the vapour barrier and the terminations, and moves the quality check to a point where a defect can still be corrected easily.

The cost is that the lift becomes more delicate — a clad assembly cannot be slung anywhere convenient, and the rigging has to be planned so the finish arrives intact.

Execution#

The lift was carried out at night, when site traffic and adjacent operations were at their lowest. Night lifting brings its own requirements: lighting to a standard where the rigging team can actually see the load, a tighter exclusion zone, and a briefing that assumes nobody improvises in the dark.

Result#

The tank was set, connected and handed over with the insulation system intact and inspected before erection rather than after.

More work

Large horizontal process vessel with insulation and metal cladding being installed
Insulation & Cladding

Process Vessel Insulation & Cladding

Thermal insulation and stainless cladding of a large horizontal process vessel, detailed for thermal movement and long-term…

Next step

Have a scope to price, or a plant to keep running?

Send us the drawings, the shutdown window, or just the problem. We will come back with a scope, a method and a number.